HomeMy WebLinkAbout1621 Herbie Cir Inspection.docSEDIMENTATION INSPECTION REPORT
CATAWBA COUNTY UTILITIES & ENGINEERING DEPARTMENT
PO Box 389, Newton, NC 28658
(828) 465-8161 FAX (828) 465-8392
Project Herbie CIR Project Number case-3-11-2555
Person Financially Responsible Alex S Harrill Construction Inc
Address 617 N Center St, Hickory, NC 28601
1. Project Location 1621and 1613 Herbie Cir, Newton Pictures: Prints Slides Digital Video
2. Weather and Soil Conditions 50's, clear skies, soil wet, but workable
3. Is site currently under notice of violation? Yes No If no, check violations below:
5. Violations (refer to Catawba County Local Ordinance Chapter 31):
a. No approved plan g. Inadequate buffer zone
b. Failure to follow approved plan h. Graded slopes and fills too steep
c. Failure to submit revised plan i. Unprotected exposed slopes
d. Failure to provide adequate groundcover j. Failure to maintain erosion control measures
e. Insufficient measures to retain sediment on site k. Other (describe):
f. Failure to take all reasonable measures
6. Phase of Grading
a. rough grading complete b. final grading complete
Description:
7. Potential NPDES Permit violation? Yes No Describe See below
8. Has sedimentation damage occurred? Yes If yes, where? (check all that apply) No
Lake/natural watercourse on the tract Lake/natural watercourse off the tract Other property Road/walkway
Description: Slight sediment has gone onto neighboring property to the southwest through the pipe under Herbie Cir. Slight sedimnet in the roads
Degree of damage: Slight Moderate Severe
9. Contact made with (name) Title
Inspection report given or sent to Person Financially Responsible. Date given/sent: 7 March 2011
10. Corrective actions needed: Install measures in the ditch to prevent futher erosion and sediment from leaving the site. Recommend installing inlet and outlet protection on the driveway
pipe and using an erosion control blanket/liner to stabilize the ditch. Clean of the sediment from the road and install measures to prevent sediment from getting onto the road.
11. Comments:
Report by: Ed Barton Others present:
Date of inspection: 7 March 2011 Time arriving at site: 1000 Time leaving site: 1025
cc: , ,