SEDIMENTATION INSPECTION REPORT CATAWBA COUNTY UTILITIES & ENGINEERING DEPARTMENT PO Box 389, Newton, NC 28658 (828) 465-8161 FAX (828) 465-8392 IN VIOLATION Yes IN COMPLIANCE Project
Maiden Fire Dept. Project Number ECPC-1-11-14240 Person Financially Responsible Apple Address 1 Infinite Loop, Cupertino, CA 95014 1. Project Location 5911 Startown Rd, Maiden, NC 28650
Pictures: Prints Slides Digital Video 2. Weather and Soil Conditions Warm, dry 3. Is site currently under notice of violation? Yes No If no, check violations below: 5. Violations (refer
to Catawba County Local Ordinance Chapter 31): a. No approved plan 31-4 ( c ) g. Inadequate buffer zone 31-5 (a) (1) b. Failure to follow approved plan 31-5 (f) h. Graded slopes and
fills too steep 31-5 (b) c. Failure to submit revised plan 31-6 (m) i. Unprotected exposed slopes 31-5 (b) d. Failure to provide adequate groundcover 31-5 (d) j. Failure to maintain
erosion control measures 31-13 e. Insufficient measures to retain sediment on site 31-7 (e) k. Notice of activity initiation 31-6 (j) f. Failure to take all reasonable measures 31-4
(d) l. Other (describe): 6. Phase of Grading a. rough grading complete b. final grading complete Description: 7. Potential NPDES Permit violation? Yes No Describe 8. Has sedimentation
damage occurred? Yes If yes, where? (check all that apply) No Lake/natural watercourse on the tract Lake/natural watercourse off the tract Other property Road/walkway Description: Degree
of damage: Slight Moderate Severe 9. Contact made with (name)John Cunningham/Holder Construction, Christine Brown/McGill Title Project Manager Inspection report in case file due to no
activity given or sent to Person Financially Responsible. Date given/sent: 2-18-11 Virbally 10. Corrective actions needed: Submit an adequate sedimentation and erosion control plan for
approval, covering all areas disturbed or to be disturbed. Submit a revised sedimentation and erosion control plan for approval for the following areas: Install all sedimentation and
erosion control measures as shown on the approved plan, including but not limited to the following locations: Install temporary sediment traps, basins and rock dams and associated diversions
as shown on the approved plan, including but not limited to the following locations: Install erosion and sediment control devices sufficient to retain sediment on the tract: Install
adequate drop inlet protection as shown on the approved plan, including but not limited to the following locations: Provide adequate temporary or permanent ground cover on all graded
slopes where rough or fine grading has been completed for 21 calendar days, including the following areas: Slopes of sediment basin need to be stabilized with temp. ground cover. Provide
adequate permanent ground cover on all areas where development has been completed for 15 working or 90 calendar days, whichever is shorter (15 working or 60 calendar days, whichever
is shorter, in High Quality Waters): Maintain all sedimentation and erosion control measures as specified in the approved plan and as required to prevent sedimentation damage including
the following locations: 11. Comments: This is my first site inspection. John is contacting Neill Grading to stabilized the basin. I also spoke with Christine Brown with McGill. She
is to call and meet me on site next week. Matt Hovis is the supervisor for Neill Grading who will be on site. I ran into Jan Wilson on another job site 2-21-11 and he said they were
stabilized the slopes of the basin 2-22-11.
No activity since last inspection: Report by: Kim Sue Others present: Date of inspection: 2-18-11 Time arriving at site: 9:30 Time leaving site: 10:05 cc: , ,