HomeMy WebLinkAbout2389 29th Ave Dr NE 4-22-10.pdf
SEDIMENTATION INSPECTION REPORT CATAWBA COUNTY UTILITIES & ENGINEERING DEPARTMENT PO Box 389, Newton, NC 28658 (828) 465-8161 FAX (828) 465-8392 Project Single Family Dwelling Project
Number Case-4-10-1700 Person Financially Responsible Ben Griffin Realty & Auction Address 606 College Ave, Lenoir, NC 28645-5403 1. Project Location 2389 29th Ave Dr NE, Hickory, NC
Pictures: Prints Slides Digital Video 2. Weather and Soil Conditions Warm, dry 3. Is site currently under notice of violation? Yes No If no, check violations below: 5. Violations (refer
to Catawba County Local Ordinance Chapter 31): a. No approved plan 31-4 ( c ) g. Inadequate buffer zone 31-5 (a) (1) b. Failure to follow approved plan 31-5 (f) h. Graded slopes and
fills too steep 31-5 (b) c. Failure to submit revised plan 31-6 (m) i. Unprotected exposed slopes 31-5 (b) d. Failure to provide adequate groundcover 31-5 (d) j. Failure to maintain
erosion control measures 31-13 e. Insufficient measures to retain sediment on site 31-7 (e) k. Notice of activity initiation 31-6 (j) f. Failure to take all reasonable measures 31-4
(d) l. Other (describe): Install a construction entrance 6. Phase of Grading a. rough grading complete b. final grading complete Description: 7. Potential NPDES Permit violation? Yes
No Describe 8. Has sedimentation damage occurred? Yes If yes, where? (check all that apply) No Lake/natural watercourse on the tract Lake/natural watercourse off the tract Other property
Road/walkway Description: Degree of damage: Slight Moderate Severe 9. Contact made with (name)n/a Title Inspection report in case file due to no activity given or sent to Person Financially
Responsible. Date given/sent: 4-27-10 10. Corrective actions needed: Install a construction entrance Submit an adequate sedimentation and erosion control plan for approval, covering
all areas disturbed or to be disturbed. Submit a revised sedimentation and erosion control plan for approval for the following areas: Install all sedimentation and erosion control measures
as shown on the approved plan, including but not limited to the following locations: Install temporary sediment traps, basins and rock dams and associated diversions as shown on the
approved plan, including but not limited to the following locations: Install erosion and sediment control devices sufficient to retain sediment on the tract: Install adequate drop inlet
protection as shown on the approved plan, including but not limited to the following locations: Provide adequate temporary or permanent ground cover on all graded slopes where rough
or fine grading has been completed for 21 calendar days, including the following areas: Provide adequate permanent ground cover on all areas where development has been completed for
15 working or 90 calendar days, whichever is shorter (15 working or 60 calendar days, whichever is shorter, in High Quality Waters): Maintain all sedimentation and erosion control measures
as specified in the approved plan and as required to prevent sedimentation damage including the following locations: 11. Comments: Install a construction entrance No activity since last
inspection: Report by: Kim Sue Others present: Date of inspection: 4-22-10 Time arriving at site: Time leaving site: cc: , ,