SEDIMENTATION INSPECTION REPORT CATAWBA COUNTY UTILITIES & ENGINEERING DEPARTMENT PO Box 389, Newton, NC 28658 (828) 465-8161 FAX (828) 465-8392 Project Grading Project Number EVO2009-00001
Person Financially Responsible Burgin -Hickory Properties Address PO Box 2610 Hickory, NC 28603 1. Project Location McDonald Pkwy SE Hickory Pictures: Prints Slides Digital Video 2.
Weather and Soil Conditions Workable 3. Is site currently under notice of violation? Yes No If no, check violations below: 5. Violations (refer to Catawba County Local Ordinance Chapter
31): a. No approved plan 31-4 ( c ) g. Inadequate buffer zone 31-5 (a) (1) b. Failure to follow approved plan 31-5 (f) h. Graded slopes and fills too steep 31-5 (b) c. Failure to submit
revised plan 31-6 (m) i. Unprotected exposed slopes 31-5 (b) d. Failure to provide adequate groundcover 31-5 (d) j. Failure to maintain erosion control measures 31-13 e. Insufficient
measures to retain sediment on site 31-7 (e) k. Notice of activity initiation 31-6 (j) f. Failure to take all reasonable measures 31-4 (d) l. Other (describe): 6. Phase of Grading a.
rough grading complete b. final grading complete Description: 7. Potential NPDES Permit violation? Yes No Describe 8. Has sedimentation damage occurred? Yes If yes, where? (check all
that apply) No Lake/natural watercourse on the tract Lake/natural watercourse off the tract Other property Road/walkway Description: Mud washing under McDonald Parkway Degree of damage:
Slight Moderate Severe 9. Contact made with (name)Dwight and Kevin Title Job Supervisors Inspection report in case file due to no activity given or sent to Person Financially Responsible.
Date given/sent: 9/24/09 10. Corrective actions needed: EXTERIOR SLOPES AND ANY AREA AT FINAL GRADE NEEDS TO HAVE PERMANANT OR TEMPORARY GROUND COVER. CONSTRUCTION ENTRANCE NEEDS TO
BE MAINTAINED AND/OR REINSTALLED. NEED A UPDATED REVISED PLAN OF SITE TO INCLUDE SCOPE OF WORK FOR THE INSTALLATION OF THE PIPE LEADING TO THE DOT RIGHT-OF WAY. CLEAN OUT BOTH SEDIMENT
BASINS AND STABALIZE SLOPES. STABALIZE EXTERIOR SLOPS ON BACK SIDE OF PROJECT. INSTALL ADDITIONAL TEMPORARY OR PERMANT GROUND COVER UNDER BILLBOARD TO PREVENT SEDIMENT FROM LEAVING SITE.
Submit an adequate sedimentation and erosion control plan for approval, covering all areas disturbed or to be disturbed. Submit a revised sedimentation and erosion control plan for approval
for the following areas: updated revisions to include pipe installation onto DOT right of way. Install all sedimentation and erosion control measures as shown on the approved plan, including
but not limited to the following locations: Install temporary sediment traps, basins and rock dams and associated diversions as shown on the approved plan, including but not limited
to the following locations: Install erosion and sediment control devices sufficient to retain sediment on the tract: Install adequate drop inlet protection as shown on the approved plan,
including but not limited to the following locations: Provide adequate temporary or permanent ground cover on all graded slopes where rough or fine grading has been completed for 21
calendar days, including the following areas: Any area which will not be under construction Provide adequate permanent ground cover on all areas where development has been completed
for 15 working or 90 calendar days, whichever is shorter (15 working or 60 calendar days, whichever is shorter, in High Quality Waters): Maintain all sedimentation and erosion control
measures as specified in the approved plan and as required to prevent sedimentation damage including the following locations:
11. Comments: No activity since last inspection: Report by: Ronda Gomez Others present: Toni Norton, Kim Sue, Ed Barton, Charlie Whaley Date of inspection: 9/23/09 Time arriving at site:
11:00 Time leaving site: 11:35 cc: Huffman Grading , ,